Click Icons to Visit Sponsor Web Sites
Vol. XI Issue III - March 2009
![]()
Project Management eJournal
We Didn't Do a Good Project Schedule
By Lonnie Pacelli
I can remember vividly my very first project schedule. My manager gave me the mission statement and an overall timeframe he thought it should take for me to complete the project. I diligently broke the schedule down to lower levels of detail. I continued to divide the overall timeframe among the tasks and assigned people to the tasks. I worked for days on end with my face buried in a computer screen developing the schedule. What I ended up with was a horrendously detailed project plan that had no logical dependencies identified, people being asked to complete 40-hour tasks in 15 minutes, and some people being asked to work 200 hours per week to get their work done. But by golly, the schedule met my manager’s timeframe request.
Sadly enough (for me), this is a very true story but one that I don’t think is too terribly uncommon. It’s pretty easy to ignore reality at times when you’re developing a schedule and to skip some fundamental steps in completing your schedule. You may get everything to look good on paper, but the result may deviate significantly from reality.
How it happens:
The project schedule was either too detailed or not detailed enough – A project schedule is only effective when it is able to help you know that everything is on track and that you’re going to be able to complete the work on time. When your activities are at too high a level, you risk losing accountability, missing out on key dependencies or expose yourself to “90% complete syndrome” when the team reports progress that is not real. When your activities are at too low a level, you can frustrate your team members by unduly micro-managing them, creating a greater administrative headache for yourself, and confusing the team with an excessive number of activities to manage. Either of these can spell schedule slippage and can severely impact successful project completion.
I’ve learned to use two rules of thumb when defining the appropriate level of detail for a project plan:
-
Can the activity be assigned to a single person to complete the activity?
-
Can the activity be completed in less than 40 hours?
Let me explain my question rationale. In the first question, I have found that explicit, clear lines of ownership are vital to ensuring that activities are completed. Whenever there is an activity assigned to “the team” or some other group of people there is no single point of accountability thus no one truly owns the task. Therefore each and every task should have a named person that takes the heat if the task isn’t completed on time.
Read Complete PM Tips & Techniques Paper >>
About the Author
Lonnie Pacelli is an internationally recognized project management and leadership author and consultant. Lonnie has over 20 year’s leadership expertise as an executive, project manager, developer, tester, analyst, trainer, consultant, and business owner. During his 11 years at Accenture he built leadership expertise consulting with many Fortune 500 companies including Motorola, Hughes Electronics, and Northrop-Grumman. During his nine years at Microsoft he continued building leadership expertise through development of some of Microsoft’s internal systems, led their Corporate Procurement group, managed their Corporate Planning group, and led company-wide initiatives on Continuous Fiscal Improvement and Training Process Optimization. He has successfully implemented projects ranging from complex IT systems to process re-engineering to business strategies. Read more about Lonnie, subscribe to his newsletter, see his books and articles, and get lots of free self-study seminars, webcasts and resources at http://www.leadingonedge.com.
|
PM World Today™ is a trademark of pmforum Inc.
PMWT™ is a trademark of pmforum Inc.
The information on this web site was checked for accuracy and authenticity when last updated. If there is any accidental infringement of copyright, the publisher of this site apologize for their actions, and would like to be notified. In addition, the publisher of this site cannot bear responsibility for the actions or the results of action of individuals or companies arising from use of information and advice contained within it.
PM World Today Privacy Policy Terms and Conditions.
© Copyright 2008 PM World Today


