July 20, 2008
Dear Editor:
Oh my G** ! We have met the enemy and, you got it, us!
Astounding! This mis-information cannot stand!
I know Lee and I thought I knew Fred. I guess not. I regretfully have misjudged both of them.
How could 2 esteemed members of PMI, and PMP’s no less, be so misinformed ? As for Lee and his misconceptions about work-packages, I will give him the benefit of my doubts and ascribe his mischaracterization of work-packages to a sloppy choice of words. When he becomes aware of his transgressions he will be vigorously [and humorously] in his acknowledgement that of course he knew better.
And Fred, the PMBoK has it RIGHT ! The fact that most practitioners don’t do what they should do
does not make the Guide to the PMBoK wrong! For example, only one in eight construction contractors even consider resources in their work plans at all and most of those few never level those resources so that their plan and schedule will be a better representation of how the work will be performed on the site or in the shop as the case may be. Does this make resources immaterial to performing the work in a cost efficient way? Of course not because only with resources do we do the work. And further, “no one makes Activity Lists”
Pogo was right-on here too. You have to make the Activity Lists for each work-package because this is where, and, when you give a complete description of the work to be done by each schedule activity since the 36-48 character limitation in Primavera and most other scheduling programs preclude a complete, unequivocal description.
Also recorded on the Activity List are the scope of work, the estimated resources needed, the estimated work-day durations along with which work calendar is planned for computing the calendar-day span of the activity, and most importantly what assumptions were made regarding the estimate of resources and calendars. All of this activity information MUST be recorded at the start of the project to support whatever challenges may come along, usually in the defense of claims or the repudiation of them.
The best way for the team to capture all this is by using a simple spreadsheet that is completed for each activity and organized by work-package. I use such a ‘list’ that can record up to 4 activities per page. [I’ll send it by email to every one who wants it. earl_bg@yahoo.com ] The ‘list’ is then my tool for preparing the logic diagram for each work-package and then these 2 documents are input to my PMIS database. With projects of hundreds to several thousands of activities no one can remember all the data that goes into preparing a work plan and schedule. And the ‘Activity List’ is used to validate the PMIS database before any analysis is made.
As usual, Bob Youker has it right!
Class dismissed!
Yes, we have met the enemy !
Earl Glenwright, BS, MBA, PSP
Registered Professional Engineer, Master Scheduler
Citizen of USA, part-time resident of Bulgaria
On project assignment in Gabon